The underground machine room of the Guan-wu power plant had been in use for a long time. A sudden water inrush occurred, which escalated rapidly.
Our company adopted a Double-Packer composite grouting method combined with polyurethane resin sealing technology to carry out treatment work such as sealing water inflow from rock fissures, reinforcing underground structures, and rebuilding surface layers.
This effectively eliminated the danger of water inflow on the sidewalls and foundation, ensuring the safety of the underground structures.